MANILA North Harbour Port, Inc (MNHPI) should complete construction of a 52-hectare dock at the North Harbor by 2015 as stipulated in its contract, according to the Philippine Ports Authority (PPA).

PPA refused to extend the deadline by two years as requested by MNHPI.

In Resolution No. 2254 dated June 2, PPA noted MNHPI’s construction plan covering January 2012 to June 2017 was “way beyond the three-year completion date as provided in the terms of reference for the modernization of the Manila North Harbor.” The resolution noted construction was originally set to start in 2010 for completion in 2013 but delays pushed it back.

You May Also Like

Laguna Lake Highway’s new 2-lane segment in Taguig opens

The newly constructed 3.2-kilometer eastbound portion of the Laguna Lake Highway in Taguig City is now open to the public, according to the Department…

New MICP, POM, Subic district collectors, x-ray inspection chief take up posts

The Bureau of Customs (BOC) has new district collectors for the ports of Manila, Subic, and Manila International Container Port (MICP), as well as…

Draft rules on PNP-controlled chemicals released next month

The draft memorandum circular that will clarify the list of chemicals under the Philippine National Police’s (PNP) control and detail how applicants can obtain…

Expats eyed to improve efficiency at Indonesia’s ports

Indonesia’s state-owned port operator PT Pelindo II is seeking to recruit foreign executives to improve the management and efficiency of its ports. Company CEO…