MANILA North Harbour Port, Inc (MNHPI) should complete construction of a 52-hectare dock at the North Harbor by 2015 as stipulated in its contract, according to the Philippine Ports Authority (PPA).

PPA refused to extend the deadline by two years as requested by MNHPI.

In Resolution No. 2254 dated June 2, PPA noted MNHPI’s construction plan covering January 2012 to June 2017 was “way beyond the three-year completion date as provided in the terms of reference for the modernization of the Manila North Harbor.” The resolution noted construction was originally set to start in 2010 for completion in 2013 but delays pushed it back.

You May Also Like

Marina details latest strategy to improve connectivity, reduce regulatory burden

The Maritime Industry Authority (Marina) has listed its plans and programs to accomplish its aim of further connectivity, mainly by ensuring an economic, efficient,…

PPA keeps pass to billionaires’ club with P2.2B in remittances for 2015

The Philippine Ports Authority (PPA) remitted P2.187 billion to the national coffers last year, once again making it a member of the “billionaires’ club,”…

DOTr to save P9B on Taguig terminal exchange project

The Department of Transportation (DOTr) has managed to give the Philippine government P9 billion in future savings after its private partner, Ayala Land Inc.…

PPA allots lower budget for 2004

THE Philippine Ports Authority (PPA) is cutting its budget by 13% for 2004 – from P9 billion to P7.8 billion. The agency expects to…