Construction of the Gemalink-Cai Mep Port, touted to be the largest at the Cai Mep-Thi Vai port complex in Vietnam once completed, has slowed down because cargo throughput has fallen and ship calls have declined at the port complex.

Completion of the deepwater port, a joint venture between Vietnam-based Gemadept Corporation and France’s CMA-CGM, has been postponed as a result of poor business at the Cai Mep-Thi Vai port complex in the Ba Ria-Vung Tau province, according to a report by the VPA Shipping Times.

A Gemadept official said carriers have stopped sending their mother ships to the port complex and instead are sending feeder ships to transport goods to transshipment ports overseas.

The development project, whose construction was awarded to South Korea’s Dealim-SAMWHA, was initially scheduled to operate in 2013 with an estimated capacity of 1.2 million TEUs (20-foot equivalent units) a year. Gemadept, however, has decided to put off the launch of the port indefinitely until the market situation improves.

 

Photo: Brian Finifter

You May Also Like

MARPOL-mandated ship fuel oil data collection begins Jan 2019

Data collection by ships of their fuel oil consumption will start on January 1, 2019, as decreed by amendments to the International Convention for…

OOCL to boost North Europe-Asia rate

Orient Overseas Container Line (OOCL), Hong Kong’s biggest box carrier, plans to impose another freight rate hike on the North Europe-Asia trade lane in…

Customs chief orders talks with customs brokers on declarant provision

Customs commissioner Rey Leonardo Guerrero recently directed Revenue Collections and Monitoring Group deputy commissioner Atty Vener Baquiran to hold talks with the Chamber of…

DPWH assigns task force to end NLEX right of way issue

A task force has been formed by the Philippine Department of Public Works and Highways (DPWH) to speed up the acquisition of vital right-of-way…