When completed, the Alae Bypass Road will divert traffic along the busy Sayre Highway, Puerto-Alae Section, and serve as an alternate road going to Mindanao Container Terminal in Tagoloan, where cargo trucks coming from Bukidnon will be catered to directly.

The Department of Public Works and Highways (DPWH) has already finished 89.8% of the bypass road project intended to benefit motorists and cargo trucks traveling between Alae, Bukidnon and Tagoloan, Misamis Oriental in Mindanao.

DPWH Region X director Zenaida T. Tan in a statement said the Alae Bypass Road involves constructing a 10-kilometer new road, improving on a seven-kilometer existing road, and building three bridges spanning a total of 237 linear meters. The project also entails installing slope protection and drainage system components.

The bypass road will start in Barangay Casinglot, Tagoloan, pass through sitios Malaiba and Bugna in Barangay Mantibugao, and end in Barangay Alae, Manolo Fortich, Bukidnon.

When completed, the Alae Bypass Road will divert traffic along the busy Sayre Highway, Puerto-Alae Section, and serve as an alternate road going to Mindanao Container Terminal in Tagoloan, where cargo trucks coming from Bukidnon will be catered to directly.

Part of the proposed Cagayan de Oro alternate highway, the Alae Bypass Road is among the priority projects in the provinces of Misamis Oriental and Bukidnon. DPWH has received a total of P1.76 billion for the project and still needs P200 million to finish it before its slated opening in November 2019.

You May Also Like

BOC releases guidelines for submission of advance declaration to CTS

The Bureau of Customs (BOC) has issued operational guidelines on the submission by foreign carriers and their agents of the advance cargo declaration and…

Malayan Towage adds 3 tugs to salvage fleet

Philippine company Malayan Towage and Salvage Corp. has acquired three tugboats for $20 million as the company, more popularly known as SALVTUG, continuously upgrades…

BOC chief: culprits to answer for illegal release of alerted containers

Philippine Customs Commissioner Isidro Lapeña vows to make accountable the individuals involved in the unauthorized release of 105 alerted containers from the Port of…

P553M Sangley airport project calls for bidders

The Philippine Department of Transportation (DOTr) is looking for contractors to bid for the P552.867-million development project at Sangley Point, which is part of…